摘要
为提高道路施工过程中工期分析的准确度,结合风险分析理论,建立了一个新的道路工程工期风险计算方法。该法首先根据道路工程施工特点,给出了阶段允许工期、阶段工期期望、阶段工期风险率、阶段工期权重、阶段工期风险的定义;然后结合简单施工流程图,对道路工程工期风险计算方法进行讨论;最后,以佛山"一环"路堤施工过程中的工期风险计算为例,演示了该计算方法的使用过程,验证其实用性。
In order to enhance the analysis accuracy of projects duration of highways during construction period,a new method for is established road duration risk based on the risk analysis theory.Firstly,the following concepts are defined: allowable stage duration,expected according to the characteristic of road construction stage duration,risk rate of stage duration,weight of stage duration and stage time risk.Secondly,the proposed method for project duration risk of highways associated with is discussed the simple construction flow chart.Finally,taking the risk evaluation of the embankment construction process of the first ring road in Foshan as an example,the calculation process of the method is demonstrated,and its practicality is rerified.
出处
《岩土工程学报》
EI
CAS
CSCD
北大核心
2013年第S1期264-268,共5页
Chinese Journal of Geotechnical Engineering
基金
国家自然科学基金项目(51168039)
关键词
工期风险
风险分析
施工流程图
概率分布
project duration risk
risk analysis
construction flow chart
probability distribution