摘要
提出了一种水电站水击计算新方法。该方法既可提高计算精度 ,又易于建模仿真 ,并对大波动及小波动计算均可适用。仿真实验结果表明 ,新方法更准确地反映了水击极值点及整个动态过程 。
An improved method for calculating water hammer in hydropower plant was proposed,which can lessen the calculation error to a great extent.The simulation studies based on Simulink in MATLAB have obtained the accurate limits of water hammer and the entire dynamic process.The results have shown that this method will benefit the security and economy of hydropower plant operation and help the study of the dynamic process of the unit.
出处
《大电机技术》
北大核心
2004年第5期49-52,共4页
Large Electric Machine and Hydraulic Turbine