摘要
该文分析了灯泡贯流式水轮机装置的特殊性,并建立了灯泡贯流式机组甩负荷过渡过程计算的数学模型,和编制了相应的计算机程序,最后介绍了白石窑水电站甩负荷过渡过程的计算成果。
In this paper, the bulb turbine property is analyzed properly and a mathematical model is established for bulb turbine load rejection. Applying this model, the dynamic characteristics of bulb turbine load rejection at Baishiyao Hydropower Station is analyzed by using computer simulation technique.
出处
《人民珠江》
1994年第6期32-38,共7页
Pearl River
关键词
贯流式水轮机
灯泡式水轮机
甩负荷
数学模型
Bulb turbine Transient of load rejection Rotational inertia in consideration of hydraulic