陆浑水库分期洪水资源化风险分析 被引量:5

Risk Analysis of Staged Flood-water Resources Utilizationfor Luhun Reservoir
在线阅读 下载PDF
导出
摘要 结合陆浑水库实际情况在分析影响水库防洪调度主要不确定性因素的基础上,讨论了风险分析的计算方法,采用蒙特卡罗模拟技术给出了水库防洪调度风险分析的实施程序。采用陆浑水库分期运用方案,对不同频率入库洪水在不同的汛限水位下造成的洪灾风险率进行了估计。结果表明,陆浑水库前、后汛期的汛限水位均可适当抬高以增加水库的兴利库容、实现汛期的洪水资源化,为陆浑水库提供了最优分期汛限水位方案。 Uncertainty factors influencing flood operation risk are analyzed, and risk analysis methods are discussed connected the actual situation of Luhun Reservoir. The operational program of the risk analysis for reservoir's flood control operation is given used Monte-carlo simulation technology. The flood risk rate, which is caused by driven up different scheme of flood control limiting level, is assessed adopted the staged operation scheme. The results show that flood control limiting levels of the earlier and later flood stage could be driven up properly to increase the active storage and realize the Flood-water Resources Utilization. Finally, the optimal reservoir flood control limiting water levels by stage are supplied for Luhun reservoir manager's reference.
出处 《灌溉排水学报》 CSCD 北大核心 2005年第5期56-59,共4页 Journal of Irrigation and Drainage
基金 国家重点基础研究发展规划"973"项目(G199904360802)
关键词 陆浑水库 风险分析 蒙特卡罗 洪水资源化 汛限水住 Luhun reservoir risk analysis Monte-carlo flood-water resources utilization flood control limiting level
  • 相关文献

参考文献4

二级参考文献3

共引文献20

同被引文献46

引证文献5

二级引证文献52

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部