摘要
简介了现在管道穿越主要方案,提出了运用模糊层次分析法(FAHP)代替层次分析法(AHP)来优选管道穿越方案的新方法。介绍了FAHP的原理和步骤,从FAHP的步骤和原理来看,FAHP比AHP简单,而且解决了一般层次分析法标度繁琐、判断矩阵一致性难以达到的不足。用FAHP来优选四川威远河流的穿越方案,最终优选结果与实际工程采用的施工方案一致。因此,FAHP可以用于类似实际工程方案的优选,为解决此类问题提供了一种新方法。
The main project of current cross pipeline is introduced.It is proposed that a new method of FAHP is used to replace the analysis of hierachical process(AHP) for optimizing the project selection of cross pipelines.The principle and procedures of FAHP are introduced.Seeing from the procedure and principle,FAHP is simpler,by which the shortcomings of complex calibration and difficult to judge the conformance of matrix of general AHP are solved.FAHP is deployed to select the Weiyuan River pipeline crossing project,the selection result is consistent with that of actual operation.Thus a new method is provided for similar project selection.
出处
《石油天然气学报》
CAS
CSCD
北大核心
2005年第6期801-802,共2页
Journal of Oil and Gas Technology
基金
四川省重点学科建设项目(SZD0416)