“先缆后梁”施工建造自锚式悬索桥的研究 被引量:12

"Erecting Cable before Constructing Girder" Construction Method of Self-Anchored Suspension Bridges
在线阅读 下载PDF
导出
摘要 针对100~400 m中小跨度的自锚式悬索桥,提出了一种先架缆后挂梁的设计施工方案.计算了施工过程中墩顶必须承受的最大水平拉力,分析了桥墩尺寸、临时固结和稳定性等关键问题.结果表明,在中小跨度范围内,墩顶最大水平力可以由墩来承受,从而能够克服目前自锚式悬索桥'先梁后缆'施工的弊端. To expand the application range of self-anchored suspension bridges, a novel construction method was brought up for self-anchored suspension bridges with a short span ranging from I00 to 400 m. It is called as" erecting cable before constructing girder" (ECBCG) construction method and means that in the construction of a self-anchored suspension bridge the girder is constructed after the cable has been erected. The maximum horizontal force that the pier must endure was investigated, and some key problems, such as the size of the pier, the temporary join and the stabilization during construction, were discussed. The results show that the horizontal force can be acceptable for this type of bridge within a certain range of span for this method to overcome the shortcoming of the construction method of "constructing girder before erecting cable".
出处 《西南交通大学学报》 EI CSCD 北大核心 2005年第6期750-753,共4页 Journal of Southwest Jiaotong University
关键词 白锚式悬索桥 先架缆后挂梁 结合梁 self-anchored suspension bridge erecting cable before constructing girder composite girder
  • 相关文献

参考文献4

二级参考文献6

共引文献243

同被引文献81

引证文献12

二级引证文献66

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部