攀钢密地选矿厂阶段磨选工业试验 被引量:4

Industrial Test on Stage Grinding and Stage Separation in Pan Steel's Midi Concentrator
在线阅读 下载PDF
导出
摘要 攀钢矿业公司密地选矿厂多年来一直沿用1段磨选工艺流程,现已不能适应矿山向中、深部开采而带来的矿石性质变化,更难以满足集团公司对铁精矿的高质量要求。为此,在实验室试验的基础上进行了阶段磨选工业试验。所获试验指标与同期采用1段磨选工艺的生产综合指标相比,精矿铁品位由52.57%提高到54.24%,原矿磨矿台时能力由71.44 t/(台.h)提高到90.13 t/(台.h)。根据工业试验结果,全厂16个系列若全面推广应用阶段磨选工艺,铁精矿年产量将由430万t提高到500万t,且精矿铁品位大于54%,可年增经济效益1亿元以上。 The one-stage grinding-separation process that has been used for many years in Midi Concentrator of Pan Steel's Mining Co. can not suit the change in the ore properties due to the deep and middle-deep mining and needless to say, meet the Group's requirements on high quality iron concentrate. Therefore, based on the laboratory test, an industrial test on the stage grinding and stage separation process was carried out. The comparison of the test results with the production performances obtained by one-stage grinding-separation process in the same period shows that there was an increase in concentrate grade from 52.57% to 54.24% and an increase in the unit/hour grinding capacity of run-of-mine ore from 71.44 t to 90.13 t. The calculation based on the test results shows that if all the 16 production lines in the concentrator apply the stage grinding and stage separation process, the annual iron concentrate output will be raised from 4.3 Mt to 5 Mt with a concentrate grade of above 54% , which will bring an annual economic benefit increase of over 100 Myuan.
出处 《金属矿山》 CAS 北大核心 2007年第2期38-41,共4页 Metal Mine
关键词 阶段磨选 1段磨选工业试验 钒钛磁铁矿 Stage grinding and stage separation, One-stage grinding-separation process, Industrial test, Vanadium-titanium magnetite
  • 相关文献

参考文献4

  • 1两段磨矿,粗精矿再磨再选工业试验报告[R].攀枝花:攀钢矿业公司选矿厂,2003.
  • 2攀钢(集团)矿业公司选矿厂阶磨阶选初步设计说明书[R].攀枝花:攀钢矿业公司设计研究院,2004.
  • 3提高攀枝花选矿厂铁精矿品位的研究报告[R].长沙:长沙矿冶研究院,2002.
  • 4刘志雄.攀钢密地选矿厂提高铁精矿品位工业试验研究[C]//《金属矿山》杂志社.2005年全国选矿高效节能技术及设备学术研讨与成果推广交流会论文集.马鞍山:《金属矿山》杂志社,2005:224-226.

同被引文献13

引证文献4

二级引证文献18

相关作者