大采高综采工作面煤壁片帮机理及控制技术 被引量:121

Coal wall spailing mechanism and control technology of fully mechanized high cutting longwall coal mining face
在线阅读 下载PDF
导出
摘要 为控制大采高综采工作面煤壁片帮,通过理论分析、数值模拟、现场实测等研究方法。研究了大采高综采工作面煤壁片帮机理,在此研究基础上,根据淮南张集矿1215(3)大采高综采工作面具体条件,提出了俯斜开采、采用高阻力结构合理的液压支架、加快工作面推进速度、加固煤壁和及时带压移架等控制煤壁片帮技术,应用实践表明,控制煤壁片帮效果良好。 In order to control the coal wall spalling in the fully mechanized high cutting longwall coal mining face, with the theoretic analysis, numerical simulation, site measurement and other research methods, the paper studied the coal wall spalling mechanism of the fully mechanized longwall coal mining face. Based on the study and according to the certain conditions of the 1215 (3) fully mechanized high cutting longwall coal mining face in Zhangji Mine of Huainan Coal Mining Group, the paper provided the down inclined mining with the high resistance and rational structure hydraulic powered supports, with a rapid mining forward speed, coal wall reinforced technology, the pressurized powered support moving forward and other spalling control technology. The applied practices showed that the spalling control results were good.
出处 《煤炭科学技术》 CAS 北大核心 2008年第9期1-3,24,共4页 Coal Science and Technology
关键词 大采高综采 煤壁片帮 控制技术 fully mechanized high cutting longwall coal mining coal wall spailing control technology
  • 相关文献

参考文献3

二级参考文献2

共引文献39

同被引文献487

引证文献121

二级引证文献801

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部