截流工程风险模型分析研究 被引量:1

An Analysis of the Risk Models in Closure Projects
在线阅读 下载PDF
导出
摘要 分析了影响截流标准风险的各种不确定性因素,总结了各种立堵截流风险模型,并结合实际工程对不同模型的计算结果进行分析比较,寻求最优的风险分析模型,确定最经济合理的截流标准,为工程设计提供借鉴和帮助。 The uncertain factors that affect the risk of river closure criteria are analyzed and the risk models of end-dump closure are summarized in this paper. Combined with practical projects, the calculation results of these risk models are worked out and studied comparatively After this, the most optimal risk model is detected, the most economical and reasonable closure criteria are determined. The results serve as references for projects.
作者 张倩 罗伟
出处 《中国农村水利水电》 北大核心 2008年第11期72-74,共3页 China Rural Water and Hydropower
关键词 截流风险 风险率模型 截流标准 立堵截流 closure risk risk probability model criteria of river closure river closure by end dumping
  • 相关文献

参考文献8

二级参考文献19

  • 1楼叔英.二滩水电站施工导流设计[J].水电站设计,1994,10(1):47-52. 被引量:5
  • 2周宜红,胡志根.施工截流系统风险率研究[J].水电能源科学,1996,14(3):171-175. 被引量:14
  • 3周宜红,胡志根.施工截流标准的合理确定——上游有已建成的水利枢纽[J].水电站设计,1996,12(4):16-19. 被引量:1
  • 4钟登华 米子明.导流隧洞泄洪能力的可靠性分析[J].天津大学学报,2001,(3).
  • 5武汉水利电力学院 成都科技大学.水利工程施工:第2版[M].北京:水利电力出版社,1985..
  • 6松辽委水利科研所 长江委长江科学院.水工建筑物水力学原型观测[M].北京:水利电力出版社,1998..
  • 7周有忠 彭宇 李新洲.大平湾水电站二期截流试验研究及原型观测[J].泄水工程与高速水流,1997,(1).
  • 8Baukuneeht K, Nef W. Digital Simulation [ M]. Springer Verlag, 1971.
  • 9Jansson B. Random Number Generators [M]. Stocholm, 1966.
  • 10水利部.水利水电工程设计洪水计算手册[M].北京:水利电力出版社,1995,1..

共引文献57

同被引文献5

引证文献1

二级引证文献10