基于关键链的自适应缓冲设置方法研究 被引量:18

Research on the adaptive buffer sizing method based on the critical chain theory
在线阅读 下载PDF
导出
摘要 在关键链项目管理、资源受限项目调度问题的理论基础上,分析了剪贴法和根方差法两种缓冲设置方法的局限性,同时考虑到项目中不同活动的资源利用程度各有不同,结合自由时差方法,设计了一种设定项目缓冲和汇入缓冲大小的新方法.最后针对PSPLIB中的典型算例在Matlab中进行了仿真验证.结果显示,在同样对项目完工时间有足够保护的前提下,利用所提出的方法能够得到更小的缓冲时间长度,从而避免由缓冲设置不当带来的新的资源冲突. Based on the theory of critical chain proiect management and the resource-constrained project scheduling problem (RPSP), the limitations of the cut and paste method and the root square error method were analyzed firstly. Accounting for the differences of the resource utilization factor among the project's tasks, a new method of project and feeding buffer sizing method was introduced with the combination of free slack method. The validation of this method was simulated in Matlab environment based on one standard instance from the well known PSPLIB benchmark set at the end of this paper. The result shows that under the premise of the buffer size provide enough protection to the project completion time, the new method could achieve less buffer size to avoid the occurrences of resources confliction due to the buffers' improper setting.
出处 《华中科技大学学报(自然科学版)》 EI CAS CSCD 北大核心 2008年第11期80-82,共3页 Journal of Huazhong University of Science and Technology(Natural Science Edition)
基金 国家重点基础研究发展计划资助项目(2005CB724107,2007AA04Z190) 国家高技术研究发展计划资助项目(2007AA04Z110) 国家自然科学基金资助项目(70772056) 国家自然科学基金杰出青年基金资助项目(50825503)
关键词 项目管理 资源利用程度 项目缓冲 汇入缓冲 关键链 project management resource utilization factor project buffer feeding buffer critical chain
  • 相关文献

参考文献9

  • 1艾利·高德拉特,杰夫·科克斯.目标[M].北京:电子工业出版社.2006.
  • 2艾利·高德拉特.关键链[M].北京:电子工业出版社,2006.
  • 3Leach L P. Critical chain project management improves project performance[J]. Project Management Journal, 1999, 30(2): 39-51.
  • 4Elmaghraby S E, Herroelen W S, Leus R. Note on the paper resource coristrained project management using enhance theory of constraints[J]. International Journal of Project Management, 2003, 21(4): 301- 305.
  • 5刘士新,宋健海,唐加福.资源受限项目调度中缓冲区的设定方法[J].系统工程学报,2006,21(4):381-386. 被引量:70
  • 6Herroelen W S, Leus R, Demeulemeester E. Critical chain project scheduling: do not oversimplify [J]. Project Management Journal, 2002, 33(4): 48-60.
  • 7Hoel P, Sidney P, Stone C. Introduction to stochastic process [M]. Boston: Houghton Mifflin Co, 1972.
  • 8Icmeli O, Erenguc S S. A branch and bound procedure for the resource constrained project scheduling problem with discounted cash flows[J]. Management Science, 1996, 42(10): 1 395-1 408.
  • 9Tukel O I, Rom W O, Eksioglu S D. An investigation of buffer sizing techniques in critical chain scheduling[J]. European Journal of Operational Research, 2006, 172: 401-416.

二级参考文献18

  • 1Goldratt E M.Critical Chain[M].Great Barrington:The North River Press,1997.
  • 2Hagemann A G.Use of the Critical Chain Project Management Technique at NASA,Langley Research Center[C].AIAA/IEEE Digital Avionics Systems Conference-Proceedings,2001,Oct,14-18:4B11-4B110.
  • 3Rand G K.Critical chain:The theory of constraints applied to project management[J].International Journal of Project Management,2000,18:173-177.
  • 4Steyn H.An investigation into the fundamentals of critical chain project scheduling[J].International Journal of Project Management 2000,19:363-369.
  • 5Herroelen W,Leus R.On the merits and pitfalls of critical chain scheduling[J].Journal of Operations Management,2001,19:559-577.
  • 6Wei C,Liu P,Tsai Y.Resource-constrained project management using enhanced theory of constraint[J].International Journal of Project Management,2002,20:561-567.
  • 7Yeo K T,Ning J H.Integrating supply chain and critical chain concepts in engineer-procure-construct (EPC) projects[J].International Journal of Project Management,2002,20:253 -262.
  • 8Brucker P,Drexl A,Mohring R,et al.Resource-constrained project scheduling:Notation,classification,models,and methods[J].European Journal of Operational Research,1999,112:3-41.
  • 9Tavares L V.A review of the contribution of operational research to project management[J].European Journal of Operational Research,2002,136:1-18.
  • 10Tavares L V,Ferreira J A,Coelho J S.On the optimal management of project risk[J].European Journal of Operational Research,1998,107:451-469.

共引文献76

同被引文献192

引证文献18

二级引证文献95

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部