摘要 在某210m高烟囱的桩基加固工程中,采用钻孔灌注桩部分托换原有桩基的方法。介绍施工场地准备、定位、开凿桩孔、钻孔灌注桩施工、后压浆施工以及桩基检测和底板桩孔恢复的施工特点和难点。通过采取有效的质量保障措施,使烟囱桩基得到加固,从而保证上部结构的继续施工。研究结果表明该加固方法切实有效。经过定期的沉降观测,烟囱沉降均匀,符合设计规范要求。 In the foundation reinforcement of a chimney engineering with height of 210m, original pile foundations are partly underpinned with bored piles. The characteristics and difficulties are introduced during the process of construction, such as construction preparation, location, pile excavation, bored piles construction, post grouting construction, as well as foundation testing and piles recovery of bottom floor. The chimney piles are strengthened by adopting effective quality measures, which can ensure the continue construction of upper structure. The results show that the method is suitable for this engineering. After regular surveying, the pile settlements are uniform. It can meet the requirements of design cedes.
作者 王俊杰
出处 《施工技术》 CAS 北大核心 2009年第3期97-100,共4页 Construction Technology
关键词 烟囱 基础工程 加固 灌注桩 chimney foundation reinforcement bored pile
  • 相关文献

参考文献3

  • 1陕西省建筑科学研究设计院.JGJ18-2003钢筋焊接及验收规程[S].北京:中国建筑工业出版社,2003.
  • 2中国建筑科学研究院.GB50204-2002混凝土结构工程施工质量验收规范[S].北京:中国建筑工业出版社,2002.
  • 3上海市基础工程公司.GB50202-2002建筑地基基础工程施工质量验收规范[S].北京:中国建筑工业出版社,2002.

共引文献118

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部