大牛地气田东区气井产水量相对较高,华北分公司在该区对8口气井进行了PCS柱塞气举的应用,很好地解决了气井的排水问题。对试验气井周期进站压力和流量进行了分析,结合气井总体生产情况,完成了柱塞气举工作制度优化。
The water yield of the gas wells in the east zone of Daniudi Gas Field is relatively high, the North China Branch of Sinopec applied PCS plunge airlift to eight gas wells in this zone, and solved the drainage of the gas well commendably. This paper analyzes the periodic station pressure and flow rate of the testing gas well, and connecting with the general production situation, fulfils the optimization of the plunge airlift working system.
出处
《科技情报开发与经济》
2009年第11期225-227,共3页
Sci-Tech Information Development & Economy
关键词
大牛地气田
柱塞气举
工作制度优化
试验气井
Daniudi Gas Field
plunge airlift
optimization of working system
testing gas well