招徕河拱坝主要工程地质问题及处理 被引量:1

Research and Treatment on Main Engineering Geologic Problems of Zhaolaihe River Arch Dam
在线阅读 下载PDF
导出
摘要 招徕河水电站大坝为对数螺旋线型碾压混凝土双曲薄拱坝,坝址地形地质条件极其复杂。经过前期反复比较论证,确定了现坝址。针对坝基存在的主要地质问题,施工时采取科学合理的处理措施,既保证了大坝的顺利施工,缩短了建设周期,又节省了工程投资。 The dam of Zhaolaihe River hydropower station, a thin, logarithmic spiral double-curvature arch dam, is made of rolled concrete,with complex topographical and geological conditions on the position of the dam,which is chosed after many comparison and argumentation. Toward the principal engineering geological problems on the dam base, the authors took on scientific and proper measures in construction, which not only shortened time of stable construction, but also saved investment on the project.
出处 《资源环境与工程》 2009年第4期415-418,共4页 Resources Environment & Engineering
关键词 拱坝 高陡边坡 坝肩开挖 地基处理 arch dam high steep slope abutment excavation foundation treatment.
  • 相关文献

参考文献2

  • 1熊友平,姚显文,等.湖北省长阳县招徕河水利水电枢纽初步设计工程地质勘察报告[R].武汉:湖北省水利水电勘测设计院,1997.
  • 2李茂芳,孙钊,编著.大坝基础灌浆[M].第二版.北京:水利电力出版技术,1987.

同被引文献47

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部