摘要
结合京沪高速铁路四标段某路基CFG桩桩帽施工工程实例,介绍了CFG桩桩帽预制与现浇之间在施工工艺、施工工序和质量控制方面的不同,从而为今后类似的施工积累相关经验。
Combined with a roadbed CFG pile capping construction engineering example of Jinghu express high railway 4th bid section, the dif- ferences between CFG pile capping prefabrication and cast-in-place construction in construction process, construction procedure and quality con- trol, therefore accumulated related experiences for future similar eonstruetion.
出处
《山西建筑》
2010年第5期139-140,共2页
Shanxi Architecture
关键词
CFG桩桩帽
现浇与预制
对比分析
CFG pile capping, cast-in-place and prefabrication, comparison analysis