摘要
介绍我国建造在透水覆盖层上土石坝渗流量观测的现状;提出考虑技术、经济、效果、运行以及对环境影响等因素的渗流量观测设计方案的综合评价方法;实例分析表明该方法考虑因素比较全面,处理得当,易于操作,结论合理。
The current situation of seepage observation of earth and rock-fill dams on permeable overburden layer in China was introduced.A comprehensive evaluation method for seepage observation plans was proposed based on technology,economy,efficiency,operation and environmental impact.Case study indicates that the proposed method comprehensively takes factors into account and is easy and convenient to use,and the conclusion is rational.
出处
《水利水电科技进展》
CSCD
北大核心
2011年第1期42-44,73,共4页
Advances in Science and Technology of Water Resources
基金
"十一五"国家科技支撑计划(2006BAC14B05)
关键词
透水覆盖层
土石坝
渗流量观测
综合评价模型
综合评价方法
permeable overburden layer
earth and rock-fill dam
seepage observation
comprehensive evaluation model
comprehensive evaluation method