沙漠地区涵洞轻型井点降水施工技术

Culvert Construction Techniques for Light-Well Point Precipitation in Desert Regions
在线阅读 下载PDF
导出
摘要 S313线兰嘎段LJ-11标位于内蒙古南部毛乌素沙漠腹地,地层为粉细砂。为完成涵洞基坑开挖任务,经方案比选采取轻型井点降水措施。主要介绍轻型井点降水的施工设计、井点管安设、降水、施工注意事项等内容,并分析了影响降水的各种因素,提出了改进降水效果的有效途径和措施,对类似工程有借鉴意义。 The LJ Contracted Section of the Langa Section of the S313 Line is located in the hinterland of the Maowusu Desert in the southern part of Inner Mongolia,the stratum of which is fine sand.For the foundation pit of the culvert to be successfully excavated,the light-well point precipitation measures are taken through the comparison and choice of the various schemes.The construction design of the light-well point precipitation,the laying of the well-point pipes,precipitation and points for attention in the construction are introduced,with various precipitation-affecting factors and measures for improving the effects of precipitation analyzed.The project may serve as a useful reference for other similar ones.
作者 赵立军
出处 《国防交通工程与技术》 2011年第1期63-67,共5页 Traffic Engineering and Technology for National Defence
关键词 沙漠地区 涵洞 基坑开挖 轻型井点降水 井点管 desert regions culvert excavation of the foundation pits light-well point precipitation well-point pipe
  • 相关文献

参考文献2

  • 1陆仁达.公路施工手册:桥涵(上册)[M].北京:人民交通出版社,2000.
  • 2建筑施工手册编写组.建筑施工手册[M].4版.北京:中国建筑工业出版社,2003.

共引文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部