基于约束满足的板坯设计模型与求解方法 被引量:10

Modelling and algorithm for the slab designing problem based on constraint satisfaction
原文传递
导出
摘要 针对客户订单的重量需求为固定值、客户订单分配过程中有最小重量限制的板坯设计问题,建立了以最小化板坯数量为目标的约束满足模型.通过三划分问题的多项式归结,证明了该问题是强NP难的;针对问题的特殊性质,给出了变量选择策略和值选择策略;提出了基于约束满足技术的求解算法,并证明了算法的收敛性;通过数据实验对算法的有效性进行了验证. A constraint satisfaction model whose objective is to minimize the slab number was built for slab production in consideration of the slab designing problem with a fixed demand of order weight and a minimum limitation of order weight assigned in one slab. The problem was proved to be NP-hard by reducing a known NP-hard three-partition problem to the discussed problem in polynomial time. Concerning with special characteristics of the problem, variable selection strategies and value selection strategies were presented. A constraint-satisfaction-based algorithm was proposed and it was proved to be convergent. The effectiveness of the proposed algorithm was verified with simulation experiments.
出处 《北京科技大学学报》 EI CAS CSCD 北大核心 2011年第5期641-646,共6页 Journal of University of Science and Technology Beijing
基金 国家自然科学基金资助项目(No.70771008) 中央高校基本科研业务费专项(No.FRF-AS-09-007B) 宁夏医科大学特殊人才科研启动基金项目
关键词 热轧 板坯 生产计划 约束满足 变量选择 值选择 hot rolling slabs production planning constraint satisfaction variable selection value selection
  • 相关文献

参考文献12

  • 1席阳,李铁克.针对固定重量板坯的板坯设计优化算法[J].北京科技大学学报,2008,30(10):1179-1183. 被引量:6
  • 2Frlsch A M, Miguel I, Walsh T. Modeling a steel mill slab design problem//Proceedings of the 1JCAI-OI Workshop on Modelling and Solving Problems with Constraints. Seattle, 2001:39.
  • 3Hnieh B, Kiziltan Z, Miguel I, et al. Hybrid modelling for robust solving. Ann Oper Res, 2004, 130 ( 1 -.4 ) : 19.
  • 4Gargani A, Refalo P. An efficient model and strategy for the steel mill slab design problem//Proceedings of the 13th International Conference on Principles and Practice of Constraint Programming. Providence, 2007:77.
  • 5Van Hentenryck P, Michel L. The steel mill slab design problem revislted//Proceedings of the 13th International Conference on Integration of AI and OR Techniques in Constraint Programming for Combinatorial Optimization Problems. Paris, 2008.377.
  • 6Dawande M, Kalagnanam J, Lee H S, et al. The slab-design problem in the steel industry. Interfaces, 2004, 34(3) :215.
  • 7Denton B, Gupta D, Jawahir K. Managing increasing product va- riety at integrated steel mills. Interfaces, 2003, 33(2) :41.
  • 8Vonderembse M A, Haessler R W. A mathematical programming approach to schedule master slab casters in the steel industry. Manage Sci, 1982, 28(12) :1450.
  • 9Dash S, Kalagnanam J, Reddy C, et al. Production design for plate products in the steel industry. IBM J Res Dev, 2007,51 (3/ 4) :345.
  • 10孙树慧,肖拥军,李铁克.基于约束满足方法求解热轧带钢库存匹配问题[J].北京科技大学学报,2008,30(6):680-684. 被引量:4

二级参考文献19

共引文献8

同被引文献154

引证文献10

二级引证文献50

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部