船舶建造分层生产计划体系 被引量:7

Shipbuilding layered production plan system
在线阅读 下载PDF
导出
摘要 为实现船舶建造生产计划的分层、分级编制、落实与执行,提出以里程碑计划为纲、以分段吊装计划为核心的船舶建造分层生产计划体系,并用四维计划体系描述方法刻画计划之间的层次关系、任务分解关系和产品在各计划间的输入/输出关系。该计划体系综合考虑壳舾涂一体化,分别从多项目、单项目角度考虑设计与生产的协同,充分重视空间场地资源和劳动力资源的利用。它完整覆盖了造船各生产环节、生产方式、资源组织以及各管理决策层次,体现了船舶建造生产组织与管理模式特点。 The production planning of shipbuilding contained stratification, grade complation, implementation and ex- ecution. To realize these steps, according to milestone plan, the shipbuilding layered production plan system was proposed by taking segment lifting as core. The 4D plan system description method was used to depict hierarchica relation, task decomposed relation and product input/output relation between plans. By comprehensive consideration of integrated hull construction outfitting and painting, the plan system's coordination of design and production was studied from single project and multi-project respectively. The space rescoure and labor resource were utilized ade- quately. Every production link, production mode, resource management organization and each decision-making level were covered by system completely, and the features of shipbuilding production and management mode were embod- ied.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2012年第3期497-506,共10页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(60904080) 国家863计划资助项目(2009AA04Z153 2008GG1000401028) 国家科技重大专项资助项目(2009ZX01043-003-002 2009ZX01045-001-002-4)~~
关键词 四维生产计划体系 船舶建造 生产计划与控制 项目调度 4D production plan system shipbuilding production planning and control project scheduling
  • 相关文献

参考文献16

  • 1WEFore Investment Consulting Co.,Ltd.Risk analysis 2010report of the shipbuilding industry[R].Beijing:China Eco-nomic Herald Office of National Development and ReformCommission,2010.
  • 2WORTMANN J.Production management systems for one-of-a-kind products[J].Computers in Industry,1992,19(1):79-88.
  • 3LEE K,LEE J,PARK K,et al.Developing scheduling sys-tems for DAEWOO shipbuilding:DAS project[J].EuropeanJournal of Operational Research,1997,97(2):380-395.
  • 4CHEN Qiang.Center shipbuilding model study and application[D].Harbin:Harbin Engineering University,2002(in Chi-nese).
  • 5喻小光,战德臣,聂兰顺.面向船舶制造企业的多层次生产计划模型与系统[J].黑龙江大学自然科学学报,2009,26(6):770-774. 被引量:6
  • 6LIU Jianfeng.Study on ship hull construction operation strate-gy based on PWBS[D].Shanghai:Shanghai Jiaotong Universi-ty,2000(in Chinese).
  • 7续爱民,金烨.基于共享合成时间Petri网的船舶吊装过程建模[J].计算机集成制造系统,2007,13(3):465-471. 被引量:9
  • 8BAO Jinsong,HU Xiaofeng,JIN Ye.A genetic algorithm forminimizing makespan of block erection in shipbuilding[J].Journal of Manufacturing Technology Management,2009,20(4):500-512.
  • 9DUCK Y,RANJAN V.Looking-forward scheduling approachapplied in pre-erection area of a shipyard[J].Journal of ShipProduction,2007,23(1):30-35.
  • 10RANJAN V,YOON Y.Shipbuilding erection network opti-mization:a TSP method[J].Journal of Ship Production,2006,22(3):139-146.

二级参考文献12

  • 1张岩.数据解读船舶行业信息化状态[J].微型机与应用,2007,26(2):74-78. 被引量:1
  • 2HERROELEN W, DEMEULEMEESTER E, DE REYCK B. A classification scheme for project scheduling[ C ]. Project scheduling: recent models, algorithms and applications. Boston/London/Dordrecht: Kluwer Academic Publishers, 1999.
  • 3DEMEULEMEESTER E, HERROELEN W. Proiect scheduling a research handbook, norwell[ M ]. Massachusetts USA: Kluwer Academic Publishers, 2002.
  • 4LEE J K, LEE K J, PARK H K, et al. Developing scheduling systems for D + aewoo shipbuilding: DAS project[ J]. European Journal of Operational Research, 1997,97 (2) :380 - 395.
  • 5MCLEAN C,SHAO G.Simulation of shipbuilding operations[C]//Proceedings of the 2001 Winter Simulation Conference.Washington,D.C.,USA:IEEE,2001:870-876.
  • 6KIM H T,LEE J G,LEE S S.A simulation-based shipbuilding system for evaluation of validity in design and manufacturing[C]//Proceedings of IEEE International Conference on Systems,Man and Cybernetics.Washington,D.C.,USA:IEEE,2003:522-529.
  • 7LEE J K,LEE K J,PARK H K,et al.Developing scheduling systems for DAEWOO shipbuilding:DAS project[J].European Journal of Operational Research,1997,97(2):380-395.
  • 8CHUNG H,LAMB T.A generic shipyard computer model-a tool for design for production[J].Journal of Ship Production,2000,16(3):160-172.
  • 9蒋昌骏.Petri网的行为理论及其应用[M].北京:高等教育出版社,2003.
  • 10PATRICE B,GERARD B,PASCAL A,et al.Verification technique for time Petri nets[C]//Proceedings of IEEE International Conference on Systems,Man and Cybernetics.Washington,D.C.,USA:IEEE,2004:4278-4283.

共引文献13

同被引文献56

引证文献7

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部