大倾角大采高综采工作面采煤设备安装的研究 被引量:7

Research on the Installation of Coal Mining Equipment in Large Dip Angle and Large Mining Height Full Mechanized Mining Face
在线阅读 下载PDF
导出
摘要 针对新疆焦煤集团2130煤矿25221工作面地质条件恶劣,煤层倾角大,煤层赋存较厚等情况,结合现有煤矿开采技术综合考虑,决定25221工作面采用一次采全高综合机械化采煤工艺,通过对地质条件、综合机械化采煤设备的研究,制定了最佳的施工方案,实现了大倾角综采工作面综合机械化采煤设备的快速安装。 According to the situations which geological condition is bad,dip angle of coal seam is large and coal seam occurrence is thick in 25221 working face of 2130 coal mine of Xinjiang coking coal group,combining with the coal mining technology comprehensively consider,decide that use full-seam mining comprehensive mechanized coal mining technology in 25221 working face,through the study of the geological condition and the comprehensive mechanized coal mining equipment,make the best of construction project,realize the fast installation of the comprehensive mechanized coal mining equipment of large dip angle fully mechanized working face.
作者 张腾 王守法
机构地区 新疆焦煤集团
出处 《山西焦煤科技》 2012年第4期42-43,共2页 Shanxi Coking Coal Science & Technology
关键词 大倾角综采工作面 综采设备 安装 Large dip angle fully mechanized coal mining face Fully mechanized coal mining equipment Installation
  • 相关文献

参考文献1

二级参考文献3

  • 1陶弛东.采掘机械[M].北京:煤炭工业出版社,1993.
  • 2赵宏林.综采面矿压与支架设计[M].徐州:中国矿山大学出版社,1987.
  • 3煤炭工业部.采煤机械化成套设备参考手册煤[M].北京:炭工业出版社,1998.

共引文献7

同被引文献22

引证文献7

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部