Key technology for construction of connection between steel pylonand concrete pile cap of middle pylon of Taizhou Bridge 被引量:1

Key technology for construction of connection between steel pylon and concrete pile cap of middle pylon of Taizhou Bridge
在线阅读 下载PDF
导出
摘要 Taizhou Bridge is a suspension bridge with three pylons and two 1 080 m main spans. The middle pylon is a steel frame with longitudinal herringbone shape and lateral gate shape. The connection between steel pylon and concrete pile cap is a key part to transfer the huge inner force from the pylon to the foundation. Its construction quality is a critical factor to the overall structural loading of the whole bridge ; therefore the contact ratio between the bearing steel plate of pylon and concrete pile cap is required to be over 75 %. The inclined joint surface in two directions, longitudinally at 39/1 920 and laterally at 1/4, posted a challenge to the construction work. A procedure test was carried out to find an optimal construction method by comparison, and finally the post-injection method was selected as it can meet the requirement of concrete strength and contact ratio at the connection. The successful application of the post-injection method in Taizhou Bridge can nrovide an examnle and reference for similar nroiects in the future.
出处 《Engineering Sciences》 EI 2012年第3期8-11,共4页 中国工程科学(英文版)
基金 National Science and Technology Support Program of China(No.2009BAG15B02) Key Programs for Science and Technology Development of Chinese Transportation Industry(No.2008-353-332-180)
关键词 middle pylon CONNECTION steel pylon concrete pile cap contact ratio post-injection method 混凝土强度 钢塔 连接 桩帽 大桥 技术 索塔 注射方法