石人沟铁矿三期工程采矿方法选择 被引量:8

Mining method selection for Third Phase Project of Shirengou Iron Mine
在线阅读 下载PDF
导出
摘要 分析比较了石人沟铁矿三期工程选用分段空场嗣后充填法与无底柱分段崩落法的优缺点,并进行了经济技术比较。结果表明:采用分段空场嗣后充填法,较无底柱分段崩落法资源利用率高、基建投资少、效益好、占地少、不搬迁村庄、尾矿得到综合利用、井下排水量小,推荐选用分段空场嗣后充填法。石人沟铁矿需对已有的三期开拓工程做必要的调整,以满足调整后的分段空场嗣后充填法。 The advantages and disadvantages of sublevel open stoping with subsequent backfilling and sublevel caving method selected by Third Phase Project of Shirengou Iron Mine is analyzed and compared, and the economic and technical analysis is made. The results showed that: the sublevel open stoping with subsequent backfilling has the advantages as high- er resource utilization ratio, less investment in capital construction, higher benefit, less land occupation, no relocation vil- lage, comprehensive utilization of tailings, smaller water discharge than that of the sublevel caving method. So the sublevel open stoping with subsequent backfilling is recommended. Shirengou Iron Mine should make necessary adjustment for the present Third Phase Project development work to meet the sublevel open stoping with subsequent backfilling.
出处 《金属矿山》 CAS 北大核心 2013年第1期23-26,共4页 Metal Mine
关键词 分段空场嗣后充填法 无底柱分段崩落法 尾矿库 开拓系统 Sublevel open stoping with subsequent backfilling, Pillarless sublevel caving method ,Tailing pond , Development system
  • 相关文献

参考文献4

  • 1李元辉,解世俊.阶段充填采矿方法[J].金属矿山,2006,35(6):13-15. 被引量:32
  • 2《采矿设计手册》编写组.采矿设计手册[M].北京:中国建筑工业出版社,1987.
  • 3中国冶金建设集团秦皇岛冶金设计研究总院.唐钢矿业有限公司石人沟铁矿地下开采三期工程初步设计[R].秦皇岛:中国冶金建设集团秦皇岛冶金设计研究总院,2005.
  • 4中钢集团马鞍山矿院工程勘察设计有限公司.河北钢铁集团矿业有限公司石人沟铁矿200万t/a充填采矿法初步设计[R].马鞍山:中钢集团马鞍山矿院工程勘察设计有限公司,2009.

二级参考文献4

共引文献31

同被引文献59

引证文献8

二级引证文献46

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部