摘要 针对高速铁路大跨连续梁桥的结构特点,结合三水准的抗震设防目标,给出了各水准下桥梁的抗震验算指标。采用反应谱法及弹塑性时程反应分析法对一实桥进行了地震反应分析及抗震性能评价。结果表明固定墩控制该桥的抗震设计。在多遇地震作用下固定墩处于弹性状态;在罕遇地震作用下固定墩纵向进入塑性,但位移延性系数小于规范容许值,结构具有较高的延性储备。该桥的抗震能力满足三水准抗震设防目标。 Considering that earthquakes occur frequently in China,four vertical and four horizontal high-speed railway networks are planned,and 23 provincial capital cities and two-thirds of the cities with populations of more than a million are located in regions of high seismic intensity,seismic design is the controlling factor in the design of high-speed railway bridges.The differences between a high-speed railway bridge and a highway or common railway bridge lie in the following aspects: First,pier,bearing system,and displacement restrictions are required to strictly ensure that high-speed trains remain on the rails.Second,bridges make up a large proportion of the high-speed railway,and most of these bridges are viaducts and long.Third,the high-speed railway will have a major impact,being traffic intensive,high speed,high cost,and so on.Fourth,gravity piers(or hollow piers) are generally used in the substructures of such bridges,and these piers often have large section size and low reinforcement ratio.The long-span continuous bridge is the most widely used bridge type in Chinese high-speed railway construction,and the structural form of "multiple spans as one unit" is often used in this bridge type,with only one fixed pier per unit.Under earthquake force,the inertial force of the superstructure is mainly exerted on the fixed pier,so the fixed pier must meet the requirements of strength and ductility.For this reason,most fixed piers of long-span continuous bridges are reinforced concrete gravity piers.Under frequent earthquake action,piers are required to be elastic,and strength failure criterion can be used to check piers.Under rare earthquake action,because a pier would be in a plastic state,the deformation failure criteria would be used.The seismic checking index for each level is combined with the three-level seismic fortification goal based on the structural characteristics of a long-span continuous beam high-speed rail bridge.A seismic response analysis was performed on an actual bridge by use of a response spectrum method,and elasto-plastic history response analysis and seismic performance evaluation were also conducted.The results showed that the seismic design of the bridge was controlled by the fixed pier.The fixed pier is in an elastic state under low-level earthquake conditions.Under high-level earthquake conditions,however,it enters a plastic state in the longitudinal direction,but the displacement ductility factor is less than the allowable value so it has sufficient ductility capability in reserve.Therefore,the seismic capacity of the bridge meets the three-level seismic fortification goal.
出处 《地震工程学报》 CSCD 北大核心 2013年第2期226-231,共6页 China Earthquake Engineering Journal
基金 国家自然科学基金项目(51108220) 长江学者和创新团队发展计划资助项目(IRT1139)
关键词 高速铁路 连续梁桥 地震反应 延性 时程反应分析 High-speed railway Continuous beam bridge Seismic response Ductility Time-history analysis
  • 相关文献

参考文献8

二级参考文献25

  • 1张春霞,李昌铸,卢铁瑞,白红英.现行桥梁抗震设计的反应谱分析方法[J].公路交通科技(应用技术版),2008,4(9):8-10. 被引量:8
  • 2叶爱君.大跨度桥梁抗震设计.同济大学工学博士学位论文[M].-,-..
  • 3中国建筑科学研究院.建筑抗震设计规范(GB/50011-2001)[S].北京:中国建筑工业出版社,2008.
  • 4罗学海 朱葳 谢逢萱.铁路实体桥墩动力分析的简化方法.地震工程与工程振动,1982,2(3):87-95.
  • 5朱伯龙,董振祥.钢筋混凝土非线性分析[M].上海:同济大学出版社,1984.
  • 6夏修身.桥墩的弹塑性地震反应分析[D].兰州:兰州交通大学,2004.
  • 7Maragakis E. Full--Resonance Tests of a Railway Bridge[A]//Structures Congress Proceedings 1[C]. ASCE, 1996: 183 190.
  • 8铁路工程抗震设计规范(GB5011l2006)[c].北京:中国计划出版社,2006.
  • 9中华人民共和国行业标准.JTG/TB02-01-2008公路桥梁抗震设计细则[S].北京:人民交通出版社,2009.
  • 10管仲国,李建中.城市快速路高架桥抗震体系选择与经济性对比--上海浦东内环线改扩建工程[C]//第19届全国桥梁学术会议论文集(下册).jE京:人民交通出版社,2010.