大跨度偏压隧道双侧壁导坑法施工方案的优化及效果分析 被引量:1

Comparative analysis and optimization on double sidewall drift in large span unsymmetrically loaded tunnel
原文传递
导出
摘要 以京珠复线长(沙)湘(潭)高速公路邓家湾隧道为依托,通过数值计算对双侧壁导坑法原设计方案和优化方案进行对比,确定了最优方案应用于施工。现场施工与监测显示,该方案确保了隧道施工安全,加快了施工进度,因而是合理可行的。施工方案的优化,完善了双侧壁导坑法施工工艺,可为类似大跨偏压隧道的施工提供参考。 Based on Deng Jia Wan tunnel Construction in Changsha-Xiangtan expressway it carries out comparative analysis and optimization of double sidewall drift method among original design scheme and optimization scheme through numerical calculation, the optimum scheme was applied to construction. Site monitoring displays that the method ensures the safety of tunnel construction, meanwhile, it speeds up the progress of tunnel construction, so it is reasonable and feasible. It perfects the construction of double sidewall drift method technology, and offers useful references for similar large span unsymmetrically loaded tunnel.
出处 《林业建设》 2014年第1期45-50,共6页 Forestry Construction
关键词 隧道 双侧壁导坑法 数值计算 优化 监测 Tunnel double sidewall drift method numerical calculation optimization monitoring
  • 相关文献

参考文献8

二级参考文献29

共引文献98

同被引文献9

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部