摘要 自从厂网分开后,发电厂起动/备用电源若由邻近的变电站引接,除了要承担发电厂输电线路基建设备投资外,运行以后还要向电网公司长期支付昂贵的变压器基本电费,因此,各设计院和发电厂对新建项目工程反复优化设计方案,努力提高机组投产后的上网竞价能力。本文通过经济、技术和安全几个方面的比较与分析,对是否配置发电机出口断路器进行综合论述,得出发电机出口断路器配置的几点意见,可为建设全寿命周期内效益最大化高效电厂提供参考。 Since the factory after the separation of grid and power plant startup/standby power if the neighboring substation connection, in addition to responsible for power plant transmission line infrastructure investment, but also to the Power Grid Corp long-term operation after the payment of basic electricity transformer expensive, therefore, the design institute and the power plant on the new project repeated design scheme optimization, and strive to improve the generating units put into operation after the bidding capacity. This article from the comparison and analysis of several economic, technology and safety, to GCB or not discussed comprehensively, some opinions starting motor circuit breaker is arranged, which can provide reference for the construction of whole life cycle of the biggest benefits of efficient power plant.
作者 周道军
出处 《电气技术》 2016年第2期102-105,共4页 Electrical Engineering
关键词 配置 发电机断路器 火力发电厂 configure generator circuit breaker(GCB) thermal power plant
  • 相关文献

参考文献7

  • 1刘洋,李霞.600MW级机组起动/备用电源引接方式优化[J].能源与环境,2007(5):50-52. 被引量:2
  • 2DL/T 5000-2000.火力发电厂设计技术规程[S].北京:中国电力出版社,2000: 64.
  • 3沈文兰,李本,李建国.研制国产发电机断路器的主攻方向[C].中国水力发电工程学会2010年电气学术交流会.2010.
  • 4徐齐巍.大容量SF_6发电机断路器关键技术的探讨[J].智能电网,2015,3(3):201-207. 被引量:7
  • 5DL/T1073-2007,电厂厂用电源快速切换装置通用技术条件[S].
  • 6徐新平.大机组GCB方式下并网特点及分析[J].中国动力工程学会,2009: 2.
  • 7GB50660-2011大中型火力发电厂设计规范[S].2011.

二级参考文献7