换流变现场负载试验补偿电容塔设计 被引量:2

Compensation Capacitance Tower Design of Converter Transformer Field Load Test
在线阅读 下载PDF
导出
摘要 介绍了大型变压器负载试验的关键技术及电容补偿原理,以一台500 k V单相双绕组换流变为例,从试验接线、设备参数选择、补偿容量计算、试验步骤等方面分析了如何在换流站现场电源容量有限的条件下,开展换流变负载温升试验。提出了一种利用换流站已有的交流滤波器,通过更改电容塔接线方式来解决试验电源容量不足的问题,具有很好的工程实际指导意义。 Introduction was made to the key technology of large transformer load test and the principle of capacitance compensation. Tak-ing a 00 kV one-phase duplex winding converter transformer for example, this paper analyzed how to carry out the converter transformer load temperature-rise test under the condition of site limited power capacity in converter transformer station from aspects of test connection, device parameters selection, compensation capacity calculation and test procedure etc. This paper proposed to solve the kind of problem of insuffcient test power capacity by using the existing alternating current flter in converter transformer to change the capacitance wiring mode. It has good engineering practice guiding signifcance.
出处 《电工电气》 2018年第2期45-49,共5页 Electrotechnics Electric
关键词 换流变 负载试验 滤波器 补偿 converter transformer load test flter compensation
  • 相关文献

参考文献7

二级参考文献52

共引文献19

同被引文献7

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部