在普速铁路电气化改造过程中需要考虑并研究接触网的悬挂技术。论文针对当前普速电气化铁路接触网施工改造中的悬挂问题从施工原因上进行了分析,并指出了接触网悬挂施工改造的技术要点和质量控制点。
It is necessary to consider and study the suspension technology of catenary in the process of electrification transformation of normal speed railway. In view of the suspension problem in the construction and reconstruction of catenary of universal speed electrified railway, this paper analyzes the construction reasons and points out the technical points and quality control points of the construction and reconstruction of catenary.
作者
裴双飞
PEI Shuang-fei(China Railway Construction and Electrification Bureau Group Second Engineering Co.Ltd.,Taiyuan 030000,China)
出处
《工程建设与设计》
2020年第6期124-125,共2页
Construction & Design for Engineering
关键词
电气化施工改造
接触网悬挂技术
施工技术要点
质量控制点
electrification construction transformation
catenary suspension technology
construction technology key points
quality control points