110 kV变电站电力施工,会直接影响电力工程质量。变电站设备具备复杂性,会导致变电站电力施工出现问题,不仅会影响变电站运行,还会加剧安全风险。基于此,分析了110 kV变电站电力施工问题,并提出科学的处理对策,以维护110 kV变电站运行效益。
The power construction of 110 kV substation will directly affect the quality of power engineering.The complexity of substation equipment will lead to problems in substation power construction,which will not only affect the operation of substation,but also aggravate the safety risk.In this paper,we focus on analyzing the power construction problems of 110 kV substation and put forward scientific treatment countermeasures to maintain the operation efficiency of 110 kV substation,which is only.
出处
《电力系统装备》
2022年第10期39-41,共3页
Electric Power System Equipment