摘要 山西省一煤矿8059工作面运输顺槽掘进区域存在围岩失稳问题。进行数值模拟可知,掘进后40 d巷道整体垮落,F16断层周边形成围岩破碎带,竖向距离30 m。在断层影响区域采取超前注浆加固措施,将破碎围岩提前凝结,随后对治理区域进行效果考察。考察结果表明,区域顶板最大位移量59 mm,变形较小。注浆措施有效解决了该区域围岩失稳的问题。 There is a problem of surrounding rock instability in the transportation gateway excavation area of 8059 working face of a coal mine in Shanxi Province.Numerical simulation shows that after 40 d of excavation,the overall collapse of the roadway occurs,and a fractured zone of surrounding rock is formed around the F16 fault,with a vertical distance of 30 m.In the area affected by the fault,advance grouting reinforcement measures were taken to condense the broken surrounding rock in advance,and then the effect of the treatment area was investigated.The inspection results indicate that the maximum displacement of the regional roof is 59 mm,and the deformation is relatively small.The grouting measures effectively solved the problem of instability of the surrounding rock in the area.
作者 焦栓太 JIAO Shuantai(Zhaozhuang Coal Industry Co.,Ltd.,Shanxi Jinneng Holding Equipment Manufacturing Group,Changzhi 046000,Shanxi,China)
出处 《能源与节能》 2024年第3期176-179,共4页 Energy and Energy Conservation
关键词 围岩失稳 数值模拟 超前注浆 效果考察 surrounding rock instability numerical simulation advance grouting effect investigation
  • 相关文献

参考文献6

二级参考文献51

共引文献21

同被引文献10

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部