地铁深基坑开挖对旁侧并行高架桥梁的影响分析

Analysis of Influence of Deep Foundation Pit Excavation of Subway on Side Viaduct
在线阅读 下载PDF
导出
摘要 以某地铁车站深基坑工程案例为背景,介绍了深基坑的设计方案,以及对旁侧并行高架桥梁的保护方案。同时,通过数值模拟,分析了地铁深基坑施工对既有高架桥梁的影响,与现场监测数据进行对比后,验证了数值分析的可靠性。结果表明,该项目基坑开挖对既有高架桥梁的影响可控,设计方案合理。 In the case of deep foundation pit in a subway station,the design scheme of deep foundation pit and the protection scheme of the side parallel elevated bridge are introduced.At the same time,the influence of the deep foundation pit construction on the existing elevated bridge is analyzed,and then compared with the field monitoring data to verify the reliability of the numerical analysis.The results show that the influence of the foundation pit excavation in this project on the existing elevated bridge is controllable and the design scheme is reasonable.
作者 孙波 SUN Bo(China Railway Siyuan Survey and Design Group Co.Ltd.,Wuhan 430063,China)
出处 《工程建设与设计》 2025年第3期18-20,共3页 Construction & Design for Engineering
关键词 地铁深基坑 旁侧并行 高架桥梁 MJS加固 钢支撑伺服系统 subway deep foundation pit parallel side by side viaduct MJS reinforcement steel support servo system
  • 相关文献

参考文献2

二级参考文献8

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部