IF钢大包长水口堵塞原因分析与改进

CAUSE ANALYSIS AND IMPROVEMENT OF LONG NOZZLE CLOGGING DURING CONTINUOUS CASTING OF IF STEEL
在线阅读 下载PDF
导出
摘要 针对IF钢大包长水口堵塞问题,通过对长水口堵塞物、中间包、长水口耐材、钢包耐材和钢渣进行取样分析,得出长水口堵塞物为高熔点的钙铝酸盐CA2和CA6,其主要来源于钢渣。通过缩短连铸倒浇余时间、规范钢包上线前检查和精准控制连铸大包剩余钢量,有效地解决了大包长水口堵塞问题。 In response to the problem of clogging in the long nozzle,samples were taken and analyzed from the long nozzle clogging,tundish,refractory material of the long nozzle,refractory material of the ladle and steel slag.It is found that the clogging of the long nozzle is high melting point calcium aluminate CA2 and CA6,which mainly comes from steel slag.By shortening the pouring time of continuous casting,standardizing the ladle inspection before production and accurately con-trolling the remaining steel amount of the continuous casting ladle,the problem of clogging of the ladle long nozzle has been effectively solved.
作者 武志杰 程迪 范佳 韩闯闯 姜丽梅 周钢 Wu Zhijie;Cheng Di;Fan Jia;Han Chuangchuang;Jiang Limei;Zhou Gang(Handan Company,HBIS Group)
出处 《河南冶金》 2024年第6期17-19,45,共4页 Henan Metallurgy
关键词 IF钢 钢包 水口 堵塞 钢渣成分分析 IF steel Ladle Nozzle Clogging Slag composition analysis
  • 相关文献

参考文献9

二级参考文献135

共引文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部